Projects
Completed projects
Abbot Point X-50 Expansion
(Nov 2010 – Oct 2011)
- Client: NQBP
- Scope: Out loading String # 1 upgrade Train unloading – Ship loader, Integration of new system into existing plant, document control and commissioning.
- Duration: 11 months
Pump Station Upgrade
(April– August 2017)
- Client: BMA, Braeside
- Scope: Project management, Supervision and electrical upgrade of an existing pump station. Scope included the installation of a HV kiosk substation, LV substation and VVVF AC drive system. Commissioning support, redline mark-ups and document control.
- Duration: 5 Months
Dragline 28 Shutdown
(June 2019 – Sept 2019)
- Client: BMA – South Walker Creek
- Scope: Conversion of Drive Motors and Systems from DC to AC, Machine Re-Wire, Motor replacements, High Voltage System Upgrade, drawing red pen mark-ups and commissioning.
- Duration: 3 months
Coolibah Pit Restart
(December 2019 – September 2020)
- Client: BMA – Saraji Mine
- Scope: High Voltage Substation Supply and Installation, Remote Pump Station Installation, Communication Trailer Installation, drawing red pen mark-ups and commissioning.
- Duration: 6 months
CHPP MCC Upgrade
(May 2018 – July 2018)
- Client: BMA – Saraji Mine
- Scope: Removal of existing MCC’s in the CHPP Main Switch room, Installation of new MCC (4 Total), new transformer feeder cables, drawing red pen mark-ups and commissioning.
- Duration: 2 Months
Substation and Conveyor System Upgrade
(July 2020 – October 2020)
- Client: Glencore– Collinsville Mine
- Scope: Project management, Supervision and electrical installations associated with the substation upgrade, MCC changeout and various distribution boards. TLO stockpile and conveyor control system upgrades. Commissioning support and document control.
- Duration: 4 months